Chapel Road Culvert Replacement

Share Chapel Road Culvert Replacement on Facebook Share Chapel Road Culvert Replacement on Twitter Share Chapel Road Culvert Replacement on Linkedin Email Chapel Road Culvert Replacement link

Image shows road closure for Chapel Road Culvert Improvement Project. During construction, Chapel Road will be closed between Black Dog Alley and Gannon Road. Wootenaux Creek Infrastructure Improvement

Talbot County Department of Public Works will replace the culvert beneath Chapel Road at Wootenaux Creek in Easton to improve roadway safety and drainage capacity.

The project will require a temporary closure of Chapel Road between Black Dog Alley and Gannon Road while crews remove the existing culvert and install a new structure designed to support long-term roadway stability.

Due to environmental regulations, the project will utilize a bottomless culvert, which preserves the natural stream channel and aquatic habitat but requires a longer construction timeline. This design will also reduce long-term maintenance by minimizing clogging from debris and will improve roadway safety through the addition of guardrails along the corridor.



Project Photos

Image shows road closure for Chapel Road Culvert Improvement Project. During construction, Chapel Road will be closed between Black Dog Alley and Gannon Road. Wootenaux Creek Infrastructure Improvement

Talbot County Department of Public Works will replace the culvert beneath Chapel Road at Wootenaux Creek in Easton to improve roadway safety and drainage capacity.

The project will require a temporary closure of Chapel Road between Black Dog Alley and Gannon Road while crews remove the existing culvert and install a new structure designed to support long-term roadway stability.

Due to environmental regulations, the project will utilize a bottomless culvert, which preserves the natural stream channel and aquatic habitat but requires a longer construction timeline. This design will also reduce long-term maintenance by minimizing clogging from debris and will improve roadway safety through the addition of guardrails along the corridor.



Project Photos

  • Update May 15th

    Share Update May 15th on Facebook Share Update May 15th on Twitter Share Update May 15th on Linkedin Email Update May 15th link
    supporting image

    Crews have completed the installation of the bypass system, and water from the stream is now being temporarily diverted around the culvert work area. Work is currently underway on the installation of a sheet pile cofferdam to dewater the construction area.

    The removal of the three existing culverts and installation of the footing and piles for the new bottomless arch culvert are scheduled for the next few weeks.



    Crews have completed the installation of the bypass system, and water from the stream is now being temporarily diverted around the culvert work area. Work is currently underway on the installation of a sheet pile cofferdam to dewater the construction area.

    The removal of the three existing culverts and installation of the footing and piles for the new bottomless arch culvert are scheduled for the next few weeks.



  • Update April 9th

    Share Update April 9th on Facebook Share Update April 9th on Twitter Share Update April 9th on Linkedin Email Update April 9th link

    The Chapel Road Culvert Project continues to move forward as crews prepare for the next phase of construction. The team is currently working to set up the bypass system needed to safely divert the stream during construction. This step is critical to maintaining water flow while allowing work on the culvert to proceed. Road-related construction activities are expected to begin shortly as the project transitions into more visible on-site work.

    The Chapel Road Culvert Project continues to move forward as crews prepare for the next phase of construction. The team is currently working to set up the bypass system needed to safely divert the stream during construction. This step is critical to maintaining water flow while allowing work on the culvert to proceed. Road-related construction activities are expected to begin shortly as the project transitions into more visible on-site work.

Page last updated: 15 May 2026, 02:15 PM