Update June 2nd

The three original culverts have been removed, and the area has been excavated to subgrade. Aggregate base material has been placed at the new footing locations, and timber piles are currently being driven along the lines where the new concrete footings will be constructed.

The installation of the piles should be completed within approximately the next 2 weeks. After the piles are placed and the concrete footings are installed, the new precast concrete bottomless arch culvert will be positioned into place.