Update July 1

Crews completed the installation of the timber piles along the lines of the footings. The cast-in-place concrete footings have been constructed and riprap placed at the inlet and outlet ends of the culvert location.

Share Update July 1 on Facebook Share Update July 1 on X (formerly Twitter) Share Update July 1 on Linkedin Email Update July 1 link